Gaoerji Steel Structure Is Responsible For The Construction! The 50,000 Square Meter Factory Of Dianguang Technology Yueqing Intelligent Manufacturing Base Has Been Fully Completed And Delivered

  • 12/18/2023

The Yueqing Economic Development Zone production base project of Dianguang Technology (stock code: 002730), fully constructed by Gaoerji Steel Structure, officially passed completion acceptance on December 18, 2023. As the listed company’s largest and most intelligent new facility, with a total construction area of ​​50,000 square meters, upon completion will significantly increase the company’s global production capacity for explosion-proof electrical equipment, becoming a new landmark for high-end intelligent manufacturing in the Yangtze River Delta.

Today, with the installation and acceptance of the final steel beam, the production base of Dianguang Technology Group (A-share code: 002730) in the Yueqing Economic Development Zone, built by Gaoerji Steel Structure Co., Ltd., has been fully completed. This modern facility, with a record-breaking construction time of 14 months and zero accidents, marks a milestone in the strategic partnership between the two companies in the construction of high-end industrial plants.

Key Project Highlights:

✅ Largest Scale: The massive 50,000 square meter facility encompasses intelligent production workshops, an R&D center, and a multi-story warehouse, expanding Dianguang Technology’s production capacity by over 120%.

✅ Technological Breakthrough: The use of a large-span truss structure (maximum span 42 meters) creates a 15-meter-high, column-free floor space, accommodating the flexible layout of heavy equipment.

✅ Intelligent Manufacturing: 31,800 meters of pre-buried 5G and IoT pipelines lay the foundation for AGV logistics and digital twin systems.

Overcoming Challenges Demonstrates Strength:

Corrosion-Resistant Design: A customized aluminum-magnesium-zinc roofing system (three times more corrosion-resistant) was developed for the high-humidity, salt-fog environment of Yueqing’s coastal area.

Precision Assembly: 38,500 steel components were pre-assembled using BIM models, with key joint tolerances ≤1.5mm.

Efficient Construction: Utilizing the “segmented hoisting + modular welding” process, the main workshop completed the installation of 8,000 tons of steel structures in a single month.

“This factory represents a new level of intelligent manufacturing in China’s explosion-proof electrical field,” said the Chairman of Dianguang Technology at the completion ceremony. “The Gaoerji team, with millimeter-level precision and international project execution capabilities, ensured the on-schedule commissioning of our global flagship facility.”

Highlighting Strategic Value:

This project further demonstrates Gaoerji Steel Structure’s comprehensive service capabilities in the EPC (Electronic Project Construction) sector for high-end industrial plants, providing clients in strategic industries such as new energy and semiconductors with one-stop steel structure solutions from design to construction.

gaoerji build

Expand more!